×

Sabiya Combined Cycle Conversion Project-1 (250 MW)

Project : Conversion to Combined Cycle Power Project at Sabiya
Client : Ministry of Electricity and Water
Alghanim Role : Main EPC Contractor
Project Value : USD 217 Million
Duration : 32 Months EPC + 3 Years O&M
Capacity : 250 MW
Completion : 2019
Project Features:
  • 1 Steam Turbine – Alstom (GE Power) Make
  • 1 Steam Turbine Generator – Alstom (GE Power) Make
  • 1 Heat Recovery Steam Generator – Alstom (GE Power) Make
  • 1 Step Up Transformer
  • Unit Transformer, Generator Circuit Breaker, HV Cables,
    MV/LV Power Distribution system, DCS
  • Architectural, Civil & Structural Works
  • Complete Balance of plant including Electro-Mechanical Erection
  • O&M for overall plant for 3 years