Az-Zour Emergency Power Project (900 MW)
Project : | EPC Contract for Gas Turbine Power Plant at Az-Zour South, Kuwait |
---|---|
Client : | Ministry of Electricity and Water |
Main Contractor : | Alghanim International |
Project Value : | USD 1,000 Million |
Duration : | 10 Months Construction + 5 Years O&M |
Capacity : | 900 MW |
Completion : | July 2008 |
Achievement : | Project completed ahead of schedule. M/s Alstom and other major vendors commented, “The project is the fastest project in the history of gas turbines of similar size, including a 9 bay GIS”. |