KOC Booster Station BS-171

Project : Booster Station BS-171
Alghanim Role : 1. Construction related to the Electrical & Instrumentation works for this large (KWD 300 million) project.
(1.0 million meters Power Cable) 1.2 million meters Instrument Cable; 90.0 kms of Cable tray;
10,000 Instruments..

2. Pipeline Construction, Hydro testing, Caliper Pigging & Purging, Installation (total length of 95 kms)

3. 11 KV Electrical & FOC Cable Works

Client : Kuwait Oil Company (KOC) / Saipem
Project Value : Approximate USD 82.5 Million
Alghanim Role
  • Construction related to the Electrical & Instrumentation works for this large (KWD 300 million) project. (1.0 million meters Power Cable; 1.2 million meters Instrument Cable; 90.0 kms of Cable tray; 10,000 Instruments…)
  • Pipeline Construction, Hydro testing, Caliper Pigging &  Purging, Installation (total length of 95 kms)
  • 11 KV Electrical & FOC Cable Works