KNPC Az Zour Refinery Project - Civil Works & UG Piping

Project : KNPC Az Zour Refinery Project – Civil Works & UG Piping
Client : SAIPEM
Alghanim Role : Mechanical Construction Contractor for other than tanks – Package 1B
Project Value : USD 56 Million
Scope of work
  • Piping (CS / SS) : 213,496 Inch dia
  • Piping (RTRP) : 8,562 Inch dia
  • Piping erection : 170,279 Meters
  • Piping support : 725 Tons
  • Steam tracing : 122,783 metres
  • Str. Steel erection : 360 Tons
  • Eqpt. Erection : 333 Tons
  • Painting : 91,628 m2
  • Insulation : 118,268 m2