×

Sabiya CCGT-3
(935 MW)

Project : Combined Cycle Power Project
Client : Ministry of Electricity and Water
Alghanim Role : Main EPC Contractor
Project Value : USD 439 Million
Duration : 36 Months EPC + 7 Years O&M
Capacity : 935 MW
Completion : 2020
Project Features:
  • 2 Gas Turbines – Siemens SGT5-4000F
  • 2 Gas Turbine Generators-Siemens SGen5-2000H
  • 1 Steam Turbine Generator – Siemens SST5-5000
  • 1 Steam Turbine Generator – Siemens SGen5-2000H
  • 2 Heat Recovery Steam Generator
  • DCS-Siemens
  • Electrical & I&C Systems
  • State of art Architectural, Civil & Structural Works
  • Complete Balance of plant including Electro-Mechanical Erection
  • 400 kV GIS and its interconnection with existing system
  • O&M for overall plant for 7 years